Re: [802SEC] 802.15.22.3 PAR extension request
Hi Jon
We are actually planning on starting the ballot on July 20th but there is
no way to indicate that in MyProject. If you put July in, it assumes July
1, so I put August so it would at least indicate it was a future event.
It is still tight but there is time for a primary ballot and 2 recircs
(with the second recirc, if needed, starting just before or on the
submission deadline, Sept 17). I am assuming the MyProject cutover will
likely slip. That is the timeline I am working to achieve, but having
great respect for Murphy, an extension is very much advised just in
case.
Cheers
Bob
At 01:31 PM 7/15/2019 -0600, Jon Rosdahl wrote:
Hi Bob,
 I have the following response to your PAR extension request for
802.15.22.3:
Comments for the PAR Extension:
4. Submitting to the Draft to NesCom on Oct 1, 2019 after starting on Aug
1, 2019 does not seem reasonable on the surface, but I understand this
may be exceptional case. However, it will mean that the PAR will
be considered by RevCom in January 2020.
The Deadline for the 2019 November RevCom Meeting is 17 September,
2019.
Regards,
Jon
-----------------------------------------------------------------------------
Jon Rosdahl             Engineer,
Senior Staff
office: 801-492-4023 Â Â Â Â Qualcomm Technologies, Inc.
cell:Â Â 801-376-6435Â Â Â Â Â 10871 North 5750 West
        Â
          Highland,
UT 84003
A Job is only necessary to eat!
A Family is necessary to be happy!!
On Mon, Jul 15, 2019 at 6:44 AM Bob Heile
<bheile@ieee.org> wrote:
- Hi All
- I am submitting a PAR extension request for 802.15.22.3 for
consideration
- on Friday under the 48 hour rule. The PAR extension can be found at
- https://mentor.ieee.org/802.15/dcn/19/15-19-0305-00-0000-802-15-22-3-par-extension.pdf.
- The expectation is we will start SA Ballot next week. Given the
current
- SASB meeting schedule, we would need to submit the draft to RevCom no
later
- than Sept 17. While this is doable, it is extremely tight.Â
This extension
- is to cover the contingency that we are not able to submit until the
next
- RevCom meeting which would not be until after the first of the
year.
- Please let me know if you have any questions. I would like to get
this on
- the consent agenda.
- Cheers
- Bob
- Bob Heile, Ph.D
- Chair, IEEE 802.15 Working Group on Wireless Specialty Networks
- Chair IEEE 2030.5 Working Group for Smart Energy Profile 2
- Co-Chair IEEE P2030 Task Force 3 on Smartgrid
Communications
- 11 Robert Toner Blvd, Suite 5-301
- North Attleboro, MAÂ 02763Â Â USA
- Mobile: +1-781-929-4832
- email:Â Â
bheile@ieee.org
- ---
- This email has been checked for viruses by Avast antivirus
software.
- https://www.avast.com/antivirus
- ----------
- This email is sent from the 802 Executive Committee email
reflector. This list is maintained by Listserv.
Bob Heile, Ph.D
Chair, IEEE 802.15 Working Group on Wireless Specialty Networks
Chair IEEE 2030.5 Working Group for Smart Energy Profile 2
Co-Chair IEEE P2030 Task Force 3 on Smartgrid Communications
11 Robert Toner Blvd, Suite 5-301
North Attleboro, MA 02763 USA
Mobile: +1-781-929-4832
email: bheile@ieee.org