[802SEC] Clause 19 Report regarding P802.16Rev2 to Sponsor Ballot



To: 802 EC reflector
cc: 802.16 reflector

Dear EC Colleagues:

I am writing to report on the status of P802.16Rev2, per the Clause 19 Conditional Approval granted on 18 July.

Working Group Letter Ballot Recirculation #26e, including the review of P802.16Rev2/D6, ran from 24 July - 8 August. The final report is here:
<http://ieee802.org/16/ballots/ballot26>

The conditions have been met. No votes or comments were received during recirculation. The final approval ratio was 284/285.

Accordingly, I am proceeding to initiate Sponsor Ballot as soon as possible.

Regards,

Roger


Roger B. Marks
Chair, IEEE 802.16 Working Group on Broadband Wireless Access <http://WirelessMAN.org >

----------